INTERIM RESULTS FOR SIX MONTHS ENDED 30 JUNE 2026

Original announcement by lse on

Company
Zanaga Iron Ore Company Limited
Ticker
ZIOC
Exchange
LSE
Region
Republic of Congo
Primary commodity
Iron ore
Secondary commodities
None reported
Document categories
Metallurgy, Capital raise, Agreement transaction, Other
Extracted
2026-09-29 15:20:04 UTC

Analysis by Minestarters Atlas

Atlas analysis published:

Minestarters Atlas analysis

Summary

Zanaga Iron Ore Company Limited announced its unaudited interim results for the first half of 2026, highlighting a substantial increase in the Zanaga Project's NPV following an April 2026 economic update based on Direct Reduction Iron (DRI) product. The company successfully raised £5.6 million (US$7.6 million) through an equity placement and is progressing a strategic investment with Red Arc Minerals LLC, including a potential US$500 million government-backed financing. Additionally, the company commenced a bulk sampling program to confirm its revised DRI flowsheet at pilot scale, aiming to advance the project towards a Final Investment Decision.

Reasoning: The company reported strong progress on its iron ore project, including a significant NPV increase from an economic update based on DRI product, a successful equity raise, and ongoing strategic investment discussions, despite an increased interim loss.

Positive factors

  • Significant increase in project NPV following economic update
  • Successful equity raise providing funding for project advancement
  • Positive laboratory test work confirming high-grade DRI product capability
  • Progress on strategic investment and potential large-scale financing
  • Identified substantial life-of-mine cash cost savings

Negative factors

  • Continued operating loss for the period
  • Extension of strategic investment transaction timetable

Low confidence — this extraction should be reviewed alongside the original source.

Facts used in scoring: 2

Classification and evidence

Free Millingpositive · Story-specific tag

Simple, clean ore amenable to standard processing without oxidation.

Why it applies: Positive test work results confirmed the ability to produce DRI-grade pellet feed concentrate with low impurities, indicating a clean ore amenable to standard processing.

Evidence · text

“Positive test work results confirming the ability of the Zanaga Iron Ore Project (the "Zanaga Project" or the "Project") to produce DRI-grade pellet feed concentrate with low impurities”

Bench Scale Onlynegative · Story-specific tag

Only preliminary bench tests completed — no locked-cycle or pilot work.

Why it applies: The reported concentrate grades are from 'laboratory-scale DRI test work' and the bulk sampling program is designed to confirm the flowsheet at 'pilot scale', indicating the current results are not yet from pilot-scale testing.

Evidence · text

“Following successful laboratory-scale DRI test work completed in mid-2025, ZIOC commissioned detailed conceptual and feasibility-level designs to refine capital and operating cost estimates to ±20% accuracy.”

Mill Routeneutral · Story-specific tag

Processing via mill or concentrator (CIL, CIP, tank leach, flotation).

Why it applies: The project involves a 'pellet plant' and a 'concentrator complex', which are typical mill-based processing methods.

Evidence · text

“A feasibility study was completed to verify the likely costs to construct and operate both 2.5 Mtpa hot and 2.5 Mtpa cold pellet plants in the Republic of Congo.”

Single Domain Onlynegative

Testing limited to one composite or domain — representativeness not established.

Why it applies: only one composite was tested

Extracted facts

Stored fact records: 2. Some facts used in scoring do not have a stored record.

Metallurgical Results (2)

laboratoryZanaga Project · iron_oreView all details
Link to this fact

Identity

Project
Zanaga Project
Commodity
iron_ore
Region
republic of congo
Reported Region
Republic of Congo
Ticker
ZIOC

Test Work

Program Status
scoping
Test Type
laboratory
Processing Route
pellet feed production
Sample
Stage One (hematite) concentrate

Recovery

Conc. Grade
68.5
Conc. Grade Unit
%Fe

Reagents

Reagent Notes
1.05 %SiO₂, 0.47 %Al₂O₃, 0.034 %P

Review

Needs Review
No
Historical
No

Dates

Event date
2026-09-29T00:00:00.000Z

Reasoning: Laboratory test work confirmed the ability to produce high-grade DRI pellet feed concentrate from Stage One hematite with low impurities, which significantly increases the project's revenue potential.

Positive factors

  • Confirms ability to produce high-grade DRI pellet feed
  • Low impurity levels
  • Increases project revenue potential

Evidence · text

“Stage One (hematite) concentrate grade results: 68.5 %Fe, 1.05 %SiO₂, 0.47 %Al₂O₃, 0.034 %P”
laboratoryZanaga Project · iron_oreView all details
Link to this fact

Identity

Project
Zanaga Project
Commodity
iron_ore
Region
republic of congo
Reported Region
Republic of Congo
Ticker
ZIOC

Test Work

Program Status
scoping
Test Type
laboratory
Processing Route
pellet feed production
Sample
Stage Two (magnetite) concentrate

Recovery

Conc. Grade
69.1
Conc. Grade Unit
%Fe

Reagents

Reagent Notes
1.96 %SiO₂, 0.40 %Al₂O₃, 0.028 %P

Review

Needs Review
No
Historical
No

Dates

Event date
2026-09-29T00:00:00.000Z

Reasoning: Laboratory test work confirmed the ability to produce high-grade DRI pellet feed concentrate from Stage Two magnetite with low impurities, which significantly increases the project's revenue potential.

Positive factors

  • Confirms ability to produce high-grade DRI pellet feed
  • Low impurity levels
  • Increases project revenue potential

Evidence · text

“Stage Two (magnetite) concentrate grade results: 69.1 %Fe, 1.96 %SiO₂, 0.40 %Al₂O₃, 0.028 %P”

How Atlas produces this analysis

Minestarters Atlas uses automated extraction to summarize mining announcements, identify reported measurements, and classify supporting evidence. Sentiment reflects the extracted narrative and classification rules; it is an interpretation, not a reported measurement. Evidence quotes and context are provided where available. Missing data, low-confidence results, and review flags indicate limitations. Check the original publisher announcement before relying on an interpretation.